Status On-Going
Accomplishment 62.72%
Contract Cost ₱145.2M
Contract Duration 210 days

Project Progress

62.72%

Basic Information

Contract ID 25OH0093
Infrastructure Year 2025
Description RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES-LIWASANG BONIFACIO WEST OVERPASS (FLYOVER) (B01348LZ), MANILA CITY

Implementing Office Authorities

Region NCR - National Capital Region
Implementing Office South Manila District Engineering Office
Project Engineer N/A
Project Inspector N/A
Materials Engineer N/A
Approving Authority N/A

Contractor Authorities

Contractor EIGHT J'S CONSTRUCTION SERVICES (41912)
Project Manager N/A
Project Engineer N/A
Materials Engineer N/A

Financial Information

Source of Funds Regular Infra - GAA 2025 OO-1
Contract Cost ₱145,235,954.84

Contract Duration

Effectivity Date June 16, 2025
Original Expiry Date January 11, 2026
Contract Duration 210 days
Days Remaining 31 days remaining

Status & Progress

Current Status On-Going
Accomplishment 62.72%

Record Information

Created At November 26, 2025 01:16 AM
Last Updated November 26, 2025 01:16 AM