Status On-Going
Accomplishment 88.07%
Contract Cost ₱96.5M
Contract Duration 318 days

Project Progress

88.07%

Basic Information

Contract ID 25GN0035
Infrastructure Year 2025
Description CONSTRUCTION OF SHORELINE PROTECTION STRUCTURE, BARANGAY POBLACION, VALLADOLID, NEGROS OCCIDENTAL

Implementing Office Authorities

Region NIR - Negros Island Region
Implementing Office Negros Occidental 4th District Engineering Office
Project Engineer N/A
Project Inspector N/A
Materials Engineer N/A
Approving Authority N/A

Contractor Authorities

Contractor R.A. CONSTRUCTION DEVELOPMENT CORPORATION (FORMERLY: R.A. CONSTRUCTION & GENERAL MERCHANDISE) (33060)
Project Manager N/A
Project Engineer N/A
Materials Engineer N/A

Financial Information

Source of Funds Regular Infra - GAA 2025 OO-2
Contract Cost ₱96,474,108.67

Contract Duration

Effectivity Date April 10, 2025
Original Expiry Date February 21, 2026
Contract Duration 318 days
Days Remaining 72 days remaining

Status & Progress

Current Status On-Going
Accomplishment 88.07%

Record Information

Created At November 26, 2025 02:20 AM
Last Updated November 26, 2025 02:20 AM