Status On-Going
Accomplishment 73.90%
Contract Cost ₱284.1M
Contract Duration 319 days

Project Progress

73.90%

Basic Information

Contract ID 25C00476
Infrastructure Year 2025
Description ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY ROADS, MAHARLIKA HIGHWAY, PROVINCE OF NUEVA ECIJA

Implementing Office Authorities

Region Region III - Central Luzon
Implementing Office Region III
Project Engineer N/A
Project Inspector N/A
Materials Engineer N/A
Approving Authority N/A

Contractor Authorities

Contractor ED1SON DEVELOPMENT & CONSTRUCTION INC. (2400) / TRIPLE S BUILDERS INC. (43634)
Project Manager N/A
Project Engineer N/A
Materials Engineer N/A

Financial Information

Source of Funds Regular Infra - GAA 2025 OO-1
Contract Cost ₱284,091,458.86

Contract Duration

Effectivity Date April 14, 2025
Original Expiry Date February 26, 2026
Contract Duration 319 days
Days Remaining 77 days remaining

Status & Progress

Current Status On-Going
Accomplishment 73.90%

Record Information

Created At November 26, 2025 12:12 PM
Last Updated November 26, 2025 12:12 PM