Status On-Going
Accomplishment 98.90%
Contract Cost ₱9.9M
Contract Duration 90 days

Project Progress

98.90%

Basic Information

Contract ID 25JE0002
Infrastructure Year 2025
Description BASIC INFRASTRUCTURE PROGRAM (BIP) CONSTRUCTION OF ROAD, BARANGAY DATAGAN, PAGADIAN CITY, ZAMBOANGA DEL SUR

Implementing Office Authorities

Region Region IX - Zamboanga Peninsula
Implementing Office Zamboanga del Sur 1st District Engineering Office
Project Engineer Ellenita M. Castulo
Project Inspector Anecito M. Tañola
Materials Engineer Roel L. Acedillo
Approving Authority Pablo L. Escuadro, MPA

Contractor Authorities

Contractor ZMS CONST. & DEV. CORP. (FORMERLY:ZMS CONSTRUCTION (10471)
Project Manager Jesus A. Maniago Jr.
Project Engineer Ronnie B. Nayve
Materials Engineer Aljie S. Cañete

Financial Information

Source of Funds Regular Infra - GAA 2025 SSP
Contract Cost ₱9,890,017.38

Contract Duration

Effectivity Date February 14, 2025
Original Expiry Date May 14, 2025
Contract Duration 90 days
Revised Contract Duration 180 days
Revised Expiry Date August 12, 2025
Days Remaining Expired (120 days ago)

Suspension & Extension

Suspension Date March 17, 2025
Resumption Date July 13, 2025
Suspension Duration 119 days
Reason for Delay/Suspension Suspension No. 1 was effective from March 17, 2025 to April 5, 2025 due to delay in acquiring DENR permit (21 CD)
Suspension No. 2 was issued for RROW Problem and was effective from May 6, 2025 to July 12, 2025 (69 CD)
Further delays brought by Unfavorable Weather Condition
Extension Duration 90 days
Revised Expiry Date August 12, 2025

Status & Progress

Current Status On-Going
Accomplishment 98.90%

Record Information

Created At November 26, 2025 01:09 PM
Last Updated November 26, 2025 01:11 PM