Status On-Going
Accomplishment 70.07%
Contract Cost ₱4.9M
Contract Duration 150 days

Project Progress

70.07%

Basic Information

Contract ID 25JE0011
Infrastructure Year 2025
Description CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES, NRJ TO BRGY. UPPER TIMONAN- MARANGAN- KAHAYAGAN- PALILI- TIMBABOY IN SUPPORT OF ABACA HANDICRAFT PROCESSING, MIDSALIP, ZAMBOANGA DEL SUR

Implementing Office Authorities

Region Region IX - Zamboanga Peninsula
Implementing Office Zamboanga del Sur 1st District Engineering Office
Project Engineer N/A
Project Inspector N/A
Materials Engineer N/A
Approving Authority N/A

Contractor Authorities

Contractor JAMRAY BUILDERS AND ENTERPRISES (44297)
Project Manager N/A
Project Engineer N/A
Materials Engineer N/A

Financial Information

Source of Funds Regular Infra - GAA 2025 CP
Contract Cost ₱4,894,087.65

Contract Duration

Effectivity Date February 14, 2025
Original Expiry Date July 13, 2025
Contract Duration 150 days
Days Remaining Expired (150 days ago)

Status & Progress

Current Status On-Going
Accomplishment 70.07%

Record Information

Created At November 27, 2025 01:38 AM
Last Updated November 27, 2025 01:38 AM