Basic Information
Contract ID
25PF0021
Infrastructure Year
2025
Description
CONSTRUCTION OF FLOOD CONTROL STRUCTURE, SEBANG COMMUNAL IRRIGATION SYSTEM (CIS), BUGUIAS, BENGUET
Implementing Office Authorities
Region
CAR - Cordillera Administrative Region
Implementing Office
Benguet 2nd District Engineering Office
Project Engineer
N/A
Project Inspector
N/A
Materials Engineer
N/A
Approving Authority
N/A
Contractor Authorities
Contractor
NORJOHN CONSTRUCTION (47891)
Project Manager
N/A
Project Engineer
N/A
Materials Engineer
N/A
Financial Information
Source of Funds
Regular Infra - GAA 2025 OO-2
Contract Cost
₱14,660,208.06
Contract Duration
Effectivity Date
March 04, 2025
Original Expiry Date
August 18, 2025
Contract Duration
168 days
Days Remaining
Expired (114 days ago)
Status & Progress
Current Status
Completed
Accomplishment
100.00%
Record Information
Created At
November 25, 2025 03:10 PM
Last Updated
November 25, 2025 03:10 PM