Basic Information
Contract ID
25PM0013
Infrastructure Year
2025
Description
ORGANIZATIONAL OUTCOME 1 - ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/ NEW ROADS - TANUDAN-BARLIG-IFUGAO ROAD (BARLIG-BANAUE SECTION), MOUNTAIN PROVINCE
Implementing Office Authorities
Region
CAR - Cordillera Administrative Region
Implementing Office
Mountain Province 2nd District Engineering Office
Project Engineer
N/A
Project Inspector
N/A
Materials Engineer
N/A
Approving Authority
N/A
Contractor Authorities
Contractor
LATAWAN EDUARDO AP-O DEVELOPERS CONSTRUCTION SERVICES (55693)
Project Manager
N/A
Project Engineer
N/A
Materials Engineer
N/A
Financial Information
Source of Funds
Regular Infra - GAA 2025 OO-1
Contract Cost
₱29,400,000.00
Contract Duration
Effectivity Date
February 27, 2025
Original Expiry Date
September 06, 2025
Contract Duration
192 days
Days Remaining
Expired (95 days ago)
Status & Progress
Current Status
Completed
Accomplishment
100.00%
Record Information
Created At
November 25, 2025 08:32 PM
Last Updated
November 25, 2025 08:32 PM