Basic Information
Contract ID
25OI0079
Infrastructure Year
2025
Description
CONSTRUCTION OF FLOOD CONTROL STRUCTURE, ZAPOTE RIVER UPSTREAM AND ITS TRIBUTARIES, LAS PINAS CITY
Implementing Office Authorities
Region
NCR - National Capital Region
Implementing Office
Las Piñas-Muntinlupa District Engineering Office
Project Engineer
N/A
Project Inspector
N/A
Materials Engineer
N/A
Approving Authority
N/A
Contractor Authorities
Contractor
E. F. CHUA CONSTRUCTION, INC. (37826)
Project Manager
N/A
Project Engineer
N/A
Materials Engineer
N/A
Financial Information
Source of Funds
Regular Infra - GAA 2025 OO-2
Contract Cost
₱98,564,620.58
Contract Duration
Effectivity Date
March 27, 2025
Original Expiry Date
December 21, 2025
Contract Duration
270 days
Days Remaining
Expired (69 days ago)
Status & Progress
Current Status
On-Going
Accomplishment
58.07%
Record Information
Created At
November 25, 2025 09:26 PM
Last Updated
November 25, 2025 09:26 PM